A program manager discovers that two component projects are producing duplicate deliverables. What is the BEST immediate action?
-
A
Cancel the lower-priority project
-
B
Escalate to the program sponsor for resolution
-
C
Convene a governance board session to realign project scopes
-
D
Allow both projects to continue to ensure redundancy