When a program's Estimate at Completion (EAC) significantly exceeds the original Budget at Completion (BAC), the program manager should:
-
A
Ignore the variance and proceed without action
-
B
Analyze cost drivers, implement corrective actions, and communicate the revised forecast to stakeholders
-
C
Immediately terminate the program
-
D
Request additional budget without analysis