A project sponsor wants to reduce the frequency of status reports to save time. A key stakeholder, however, requires weekly updates per their engagement plan. What should the PM do?
-
A
Follow the sponsor's direction and reduce all reports
-
B
Maintain the stakeholder's agreed-upon communication frequency
-
C
Eliminate status reports entirely and use informal updates
-
D
Escalate to the PMO for a decision