In a hybrid project, the team uses a WBS for infrastructure work and a product backlog for software features. What does this approach BEST illustrate?
-
A
Inconsistent project management leading to confusion
-
B
Tailoring scope management tools to fit the nature of the work
-
C
A violation of PMI standards for scope documentation
-
D
Improper decomposition of the project scope