A project manager is developing the WBS and realizes some work elements are difficult to define at this stage. What is the BEST approach?
-
A
Wait until the project is cancelled and restart with better information
-
B
Use rolling wave planning to plan near-term work in detail and future work at a higher level
-
C
Guess at the details to fill out the WBS completely
-
D
Proceed without a WBS for the undefined portions