A project manager discovers that a key stakeholder has been requesting small feature additions directly from developers without going through change control. What should the project manager do FIRST?
-
A
Immediately stop all developer work and escalate to the sponsor
-
B
Meet with the stakeholder to explain the change control process and its importance
-
C
Accept the changes since they are small and unlikely to affect the schedule
-
D
Remove the stakeholder's access to the development team