A project manager notices that two activities on the critical path have a start-to-start dependency with a 3-day lag. If the predecessor slips by 2 days, what is the impact on the successor?
-
A
Successor slips 5 days
-
B
Successor slips 2 days
-
C
Successor is unaffected
-
D
Successor slips 3 days