A project manager is analyzing the critical path and finds that a non-critical activity has a total float of 0 days but free float of 5 days. What does this indicate?
-
A
The activity is on the critical path
-
B
Delaying this activity will delay its successor but not the project end date
-
C
The activity can be delayed 5 days without affecting any successor
-
D
The activity has a finish-to-start dependency with lag