A project manager notices that a key supplier is experiencing financial difficulties. Which risk response strategy is MOST appropriate?
-
A
Accept the risk and monitor the supplier
-
B
Transfer the risk by requiring a performance bond
-
C
Avoid the risk by canceling the contract
-
D
Exploit the risk to gain a competitive advantage