A project manager receives a change request from the seller claiming scope was unclear in the original SOW. What is the FIRST step?
-
A
Approve the change and issue a contract modification
-
B
Deny the claim since the contract has already been signed
-
C
Review the original SOW and contract to assess if the claim is valid
-
D
Escalate to senior management for a decision