A project manager learns that a vendor will deliver 2 weeks late. This risk was previously identified and a contingency plan exists. What should the PM do?
-
A
Issue a change request immediately
-
B
Activate the contingency plan and update the risk register
-
C
Escalate to senior management and wait for direction
-
D
Accept the delay and update the schedule baseline without approval