A project manager notices that a key stakeholder is consistently missing status meetings. What is the BEST first step?
-
A
Escalate to the sponsor immediately
-
B
Update the communications management plan and reach out to understand their preferred communication method
-
C
Remove them from the distribution list
-
D
Continue sending meeting invites without any changes