A project is halfway complete and two team members have a personal conflict that is affecting productivity. The project manager has tried smoothing but it hasn't worked. What should be tried NEXT?
-
A
Forcing a resolution by making a unilateral decision
-
B
Compromising so each party gives up something
-
C
Avoiding the conflict until the project ends
-
D
Escalating directly to senior management without discussion