A project manager notices that the team is consistently bypassing the change control process to make small changes. What is the BEST response?
-
A
Allow small changes to bypass the process to maintain team morale
-
B
Reinforce the importance of integrated change control and enforce the process for all changes
-
C
Report each team member to HR for non-compliance
-
D
Create a parallel informal process for minor changes