A project is delivering on time and within budget, but early user adoption data shows the product is not being used. This situation MOST likely indicates:
-
A
A risk management failure requiring immediate escalation
-
B
A benefits realization gap where delivered outputs are not producing expected outcomes
-
C
Insufficient stakeholder communication during execution
-
D
A quality management failure in the deliverable