A project manager discovers mid-project that a vendor's deliverable does not meet an industry regulatory standard. What is the BEST immediate action?
-
A
Continue the project and document the deviation for post-project review
-
B
Halt the vendor's work and issue a formal corrective action request
-
C
Notify the project sponsor and await direction before taking any action
-
D
Remove the vendor from the project and find an alternative immediately