A project manager is transitioning a traditionally managed team to agile. Stakeholders are uncomfortable with the lack of a detailed upfront plan. What is the BEST approach?
-
A
Revert to waterfall to satisfy stakeholder concerns
-
B
Create a detailed plan for the entire project before starting any sprints
-
C
Provide a high-level roadmap and demonstrate value through early working increments
-
D
Eliminate all planning ceremonies to accelerate delivery