A Scrum team consistently fails to complete all sprint backlog items by the end of each sprint. What should the team do FIRST?
-
A
Add more team members to increase capacity
-
B
Reduce sprint length to create more frequent deadlines
-
C
Inspect and adapt by examining why items are not completed
-
D
Escalate the issue to the project sponsor