A project manager identifies a risk that could delay the critical path by three weeks. The probability is low but the impact is very high. What is the BEST risk response strategy?
-
A
Accept the risk passively
-
B
Develop a contingency plan with triggers
-
C
Transfer the entire project to another team
-
D
Ignore the risk due to low probability