PMBOK - Project Management Body of Knowledge PMBOK FREE PMBOK Managing Project Risks Questions and Answers 2
A project manager identifies a risk that could delay the critical path by three weeks. The probability is low but the impact is very high. What is the BEST risk response strategy?