A general contractor issues a backcharge to a subcontractor. This typically occurs when:
-
A
The subcontractor completes work ahead of schedule
-
B
The GC incurs costs to correct, complete, or clean up after a subcontractor's failure
-
C
The owner reduces the scope of the subcontract
-
D
A subcontractor requests additional mobilization fees