General Contractor License Cheat Sheet 2026
The 30 highest-yield General Contractor License facts, distilled from real exam questions. Print it, save it as a PDF, or study it here β free, no sign-up.
50 questions
120 min time limit
70.00% to pass
- Under OSHA standards, which of the following is a 'competent person' best defined as? β A person capable of identifying hazards and with authority to take corrective action
- In project scheduling, which of the following best describes the 'Critical Path'? β The longest sequence of dependent tasks that determines the minimum project duration.
- Which IRS form is a general contractor required to issue to an unincorporated subcontractor who was paid $600 or more in a tax year? β 1099-NEC
- How often must fire extinguishers be inspected on a construction site according to OSHA? β Monthly
- What is meant by 'phased construction' in project planning? β Breaking the project into sequential stages to allow early occupancy or faster completion
- What is the minimum required distance from the edge of an excavation that spoil piles must be placed to prevent cave-ins? β 2 feet
- A contractor discovers hidden conditions on a job site that significantly increase costs. Which contract clause typically addresses this situation? β Differing site conditions clause
- What is the purpose of a 'scope of work' provision in a subcontract agreement? β To precisely define the work the subcontractor is and is not responsible for performing
- Which planning tool visually shows project tasks over a timeline using horizontal bars? β Gantt chart
- __________ is the amount of unused latex paint in solidified form. β A non-hazardous waste
- A general contractor is creating a Work Breakdown Structure (WBS) for a custom home build. Which of the following is the primary purpose of developing a WBS? β To break down the total project scope into smaller, more manageable work packages.
- A laboratory soil analysis, known as a Proctor test (ASTM D698), is performed on a soil sample from a job site. What is the primary purpose of this test? β To establish the optimal moisture content for maximum compaction.
- What is the legal significance of the 'substantial completion' date in a construction contract? β It starts the statute of limitations period and shifts insurance risk to the owner
- Soil classified as Type C under OSHA excavation standards is: β Granular or fissured soil with the highest risk of collapse
- Which fire-resistance rating is typically required for a floor-ceiling assembly separating dwelling units in a two-family residential building? β 1 hour
- What is the primary purpose of a surety bond in the construction industry? β To guarantee the contractor will fulfill contractual obligations
- Which mortar type is recommended for load-bearing exterior masonry walls in moderate climates? β Type N
- If you see that a fireproof door is needed but it is not included in the drawings, you should: β Report it to the architect immediately
- Which of the following best describes the primary purpose of a construction daily report? β To provide a legal, historical record of job site activities, progress, and conditions.
- A competent person inspects an excavation and finds standing water at the bottom. What is the correct action? β Remove workers until water is controlled
- When a project experiences a differing site condition, the contractor is MOST likely entitled to: β An equitable adjustment in contract price and/or schedule
- What is the maximum noise exposure level allowed by OSHA for an 8-hour workday without hearing protection? β 90 dBA
- When must a competent person inspect an excavation? β Before each shift and after any hazard-increasing event
- What frequency of inspection is required for excavations by a competent person? β Daily and after any hazardous condition (rain, freeze-thaw, adjacent loads)
- How much cash can be given as a deposit on a home renovation project to a contractor? β 10 % or $1000.00 whichever is less.
- A contractor discovers the water supply pressure at a residential project measures 95 psi. What corrective action is required by code? β Install a pressure reducing valve (PRV) to bring pressure below 80 psi
- Under OSHA's heat illness prevention guidance, what is the recommended action when the heat index reaches 103Β°Fβ115Β°F (high risk)? β Reduce physical demands, use engineering controls, and have a buddy system in place
- A subcontractor falls behind schedule on a critical-path activity. What is the MOST appropriate first step for the general contractor? β Issue a formal cure notice and schedule a recovery meeting
- What is 'blowout' in the context of concrete formwork? β Sudden failure of formwork under hydrostatic concrete pressure
- Under OSHA's crane safety standard, what is required before a crane operator lifts a load near its rated capacity? β Confirmation that outriggers are fully extended and set
Turn these facts into recall:
Was this helpful?