General Contractor License Exam (Business & Law Portion) — Questions and Answers
Question 1: A submittal schedule lists shop drawings, product data, and samples that must be approved before installation. Why is timely submittal management critical to the project schedule?
- Delayed submittals can create procurement delays that push back material delivery and installation activities (Correct answer)
- Subcontractors cannot mobilize until all submittals are approved by the owner
- Submittals must be filed with the building department before framing inspections
- Submittals replace the need for on-site inspections by the architect
Correct answer: Delayed submittals can create procurement delays that push back material delivery and installation activities
Long-lead material orders depend on approved submittals; delays in the review cycle can cascade into procurement delays that directly impact the construction schedule.
Question 2: What is the primary purpose of a subdrain (French drain) installed in a retaining wall?
- To anchor the wall to the retained soil
- To relieve hydrostatic water pressure behind the wall (Correct answer)
- To provide a conduit for utility lines
- To increase the wall's bearing capacity
Correct answer: To relieve hydrostatic water pressure behind the wall
A subdrain behind a retaining wall removes accumulated groundwater to prevent dangerous hydrostatic pressure buildup that could cause wall failure.
Question 3: When a contractor works directly with the owner of residential property and the contract fee is: a written agreement between the parties is necessary.
- $1,000 or more
- $2,000 or more (Correct answer)
- Any amount
- More than $2,000
Correct answer: $2,000 or more
In many states, including California, a written contract is legally required for home improvement projects when the contract price exceeds a certain threshold to protect both the homeowner and the contractor. While California's threshold is $500, $2,000 or more is a common and significant threshold in many jurisdictions for requiring a formal written agreement for residential property work.
Question 4: Under the percentage-of-completion accounting method, revenue is recognized:
- Based on the proportion of work completed to date (Correct answer)
- At the start of the contract
- When the client makes each scheduled payment
- Only when the project reaches final completion
Correct answer: Based on the proportion of work completed to date
Percentage-of-completion recognizes revenue proportionally as work progresses, matching revenue with costs incurred.
Question 5: What is the primary purpose of holding regular toolbox talks on a construction site?
- To provide a forum for workers to negotiate wages.
- To assign daily work tasks to each individual worker.
- To discuss specific job-site safety hazards and reinforce safe work practices. (Correct answer)
- To review the overall project budget with the entire crew.
Correct answer: To discuss specific job-site safety hazards and reinforce safe work practices.
Toolbox talks (or safety talks) are short, informal safety meetings held on-site. Their main purpose is to regularly communicate and reinforce safety awareness by focusing on specific hazards relevant to the current work being performed, promoting a strong safety culture.
Question 6: A contractor discovers unforeseen subsurface conditions (rock instead of soil) that significantly increase excavation costs. Which contract clause would most likely entitle the contractor to additional compensation?
- Force majeure clause
- Indemnification clause
- Differing site conditions clause (Correct answer)
- Substantial completion clause
Correct answer: Differing site conditions clause
A differing site conditions clause entitles contractors to additional compensation when actual subsurface or latent conditions differ materially from what was represented in the contract documents.
Question 7: A general contractor's license bond primarily protects:
- The contractor's personal assets
- The public and project owners from contractor defaults (Correct answer)
- The bonding company from losses
- Subcontractors from non-payment by the owner
Correct answer: The public and project owners from contractor defaults
License bonds are required to protect the public and project owners if the contractor fails to fulfill contractual obligations or violates licensing laws.
Question 8: A subcontractor's bid is missing clarifications on exclusions. What should the GC do before including it in the bid?
- Contact the subcontractor to clarify scope before bid day (Correct answer)
- Add a 20% contingency and include it
- Exclude the sub and use the next lowest
- Use the bid as submitted to stay competitive
Correct answer: Contact the subcontractor to clarify scope before bid day
The GC must clarify scope gaps with subcontractors before bid submission to avoid costly scope gaps or disputes during construction.
Question 9: What is the difference between a lump-sum contract and a unit-price contract?
- Lump-sum pays per item installed; unit-price pays a fixed total
- Lump-sum includes materials only; unit-price includes labor only
- There is no meaningful difference
- Lump-sum is a fixed total price; unit-price pays per measured unit of work (Correct answer)
Correct answer: Lump-sum is a fixed total price; unit-price pays per measured unit of work
A lump-sum contract has one agreed total price, while a unit-price contract pays based on actual quantities of work measured in the field.
Question 10: A contractor discovers that a subcontractor is misclassifying employees as independent contractors. What is the primary risk to the general contractor?
- The GC has no liability for a subcontractor's classification decisions
- Only the subcontractor faces fines
- The GC could face joint employer liability for unpaid wages and benefits (Correct answer)
- The project owner is responsible for all employment classifications
Correct answer: The GC could face joint employer liability for unpaid wages and benefits
In many jurisdictions, general contractors can be held jointly liable for subcontractor wage violations under joint employer or responsible contractor doctrines.
Question 11: A contractor's license is classified as a 'professional privilege.' This means:
- It is a right guaranteed by the U.S. Constitution
- It is granted by the state and can be taken away for cause (Correct answer)
- It transfers automatically to a new business entity
- It can never be revoked once issued
Correct answer: It is granted by the state and can be taken away for cause
A license is a privilege granted by the state, not a constitutional right, so it can be suspended or revoked if the licensee violates applicable laws.
Question 12: A general contractor is managing a project with a fixed completion date. To ensure the project stays on schedule without overallocating their limited crew, they adjust the timing of non-critical activities within their available slack or 'float'. What project management technique is being used?
- Fast-Tracking
- Crashing the Schedule
- Resource Smoothing (Correct answer)
- Resource Leveling
Correct answer: Resource Smoothing
Resource smoothing is a technique used to optimize resources by adjusting activities within their available float time, ensuring that resource usage is balanced without affecting the project's critical path or end date. In contrast, resource leveling might extend the project deadline to resolve resource conflicts.
Question 13: A general contractor is creating a Work Breakdown Structure (WBS) for a custom home build. Which of the following is the primary purpose of developing a WBS?
- To finalize the construction contract with the property owner.
- To create a marketing brochure for the finished home.
- To break down the total project scope into smaller, more manageable work packages. (Correct answer)
- To hire all the necessary subcontractors for the job.
Correct answer: To break down the total project scope into smaller, more manageable work packages.
The primary purpose of a Work Breakdown Structure (WBS) is to hierarchically decompose the total scope of a project into manageable sections or 'work packages'. This allows for better planning, cost estimating, scheduling, and control.
Question 14: What is a 'bid bond' and when is it typically required?
- A bond ensuring subcontractors are paid
- Insurance that covers workers on the project
- A performance guarantee submitted after award
- A surety bond guaranteeing the contractor will honor the bid price if awarded the contract (Correct answer)
Correct answer: A surety bond guaranteeing the contractor will honor the bid price if awarded the contract
A bid bond is a surety instrument that protects the owner if the low bidder refuses to enter the contract, typically required on public projects.
Question 15: What does 'compaction factor' refer to in earthwork calculations?
- The proctor density as a percentage of maximum dry density
- The ratio of wet to dry unit weight of soil
- The ratio of compacted fill volume to the bank (in-place) volume from which it came (Correct answer)
- The percentage of air voids eliminated during compaction
Correct answer: The ratio of compacted fill volume to the bank (in-place) volume from which it came
The compaction factor (or swell/shrinkage factor) accounts for volume changes when soil is excavated and recompacted in a new location.
Question 16: During a commercial build-out, the client decides they want to add three additional electrical outlets in an office after the drywall has been installed. The general contractor informs the client this will increase the cost and may add a day to the schedule. What document must be executed before the contractor proceeds with this additional work?
- A Change Order (Correct answer)
- A Submittal Approval
- A Request for Information (RFI)
- An Addendum
Correct answer: A Change Order
A Change Order is a formal document that amends the original contract to reflect a change in the scope of work, project cost, or schedule. Since the client's request for additional outlets alters the original scope and has cost and time implications, a signed change order is required before proceeding to ensure all parties agree to the modifications.
Question 17: A general contractor is preparing a bid for a lump-sum contract. Which cost element is most commonly overlooked that can lead to project losses?
- General conditions and overhead costs (Correct answer)
- Material quantities from the drawings
- Labor wages listed in the plans
- Subcontractor scope items
Correct answer: General conditions and overhead costs
General conditions (site trailer, supervision, temporary utilities, insurance) and overhead are frequently underestimated, eroding project profit margins.
Question 18: In soil classification, 'cohesive' soils primarily include:
- Sand and gravel
- Well-graded crushed stone
- Decomposed rock
- Clay and silt (Correct answer)
Correct answer: Clay and silt
Cohesive soils such as clay and silt have particles that stick together due to electrochemical forces rather than friction.
Question 19: Regarding trusses, Which of the following statements is untrue?
- Trusses are never used as repetitive lightweight members, such as steel bar (Correct answer)
- The trusses are often used as visual or spatial elements.
- Trusses are not limited to planar assemblies, and can be arranged as
- Trusses are also used for heavily loaded long spans requiring more structural
Correct answer: Trusses are never used as repetitive lightweight members, such as steel bar
The statement that trusses are never used as repetitive lightweight members, such as steel bar, is untrue. Trusses, particularly steel bar joists, are very commonly used as repetitive lightweight structural members for roofs and floors in various types of buildings. Their triangulated geometry allows them to efficiently span long distances while minimizing material use and weight, making them an economical and effective choice for such applications.
Question 20: When preparing a bid, why is it important to review addenda issued before bid closing?
- Addenda extend the contract duration automatically
- Addenda set subcontractor payment terms
- Addenda modify the bid documents and all bidders must price the same revised scope (Correct answer)
- Addenda list preferred subcontractors
Correct answer: Addenda modify the bid documents and all bidders must price the same revised scope
Addenda are formal revisions to bid documents, and failing to include them in your estimate can result in scope gaps or bid disqualification.
Question 21: What is the standard laboratory test used by geotechnical engineers to determine the optimal moisture content at which a specific soil type will achieve its greatest density when compacted?
- Atterberg Limits Test
- Sieve Analysis
- California Bearing Ratio (CBR) Test
- Proctor Compaction Test (Correct answer)
Correct answer: Proctor Compaction Test
The Proctor Compaction Test (either Standard or Modified) is the established laboratory method for determining the optimal moisture content and maximum dry density of a soil. This data is crucial for ensuring that fill material is properly compacted on site to provide adequate support for foundations, slabs, and pavement.
Question 22: What is the primary purpose of a vapor retarder installed in a wall assembly?
- To increase the fire resistance rating
- To provide additional thermal insulation
- To limit moisture migration into the building envelope (Correct answer)
- To act as a sound barrier between wall cavities
Correct answer: To limit moisture migration into the building envelope
Vapor retarders control moisture diffusion through wall assemblies, preventing condensation within the envelope that could lead to mold and structural damage.
Question 23: What is 'substantial completion' in a construction contract?
- Issuance of a temporary certificate of occupancy
- The stage when the work is sufficiently complete for the owner to use it for its intended purpose (Correct answer)
- Final payment to all subcontractors
- When 50% of the contract value is earned
Correct answer: The stage when the work is sufficiently complete for the owner to use it for its intended purpose
Substantial completion triggers the start of warranty periods, shifts insurance responsibilities, and is typically when liquidated damages stop accruing.
Question 24: Which soil type is considered the most stable for excavation purposes under OSHA's classification system?
- Type A (Correct answer)
- Type D
- Type C
- Type B
Correct answer: Type A
Type A soil is the most stable and cohesive, allowing for the steepest allowable slope (¾:1 horizontal to vertical).
Question 25: In many jurisdictions, state or national building codes like the IBC are adopted as the baseline. However, a city or county may enact ordinances to modify these codes for their specific region. What must these local amendments typically be based on?
- A finding that they are necessary due to local climatic, geological, or topographical conditions (Correct answer)
- A vote by the majority of general contractors in the area
- The preference of the local builders' association
- A requirement to be less restrictive than the state code to encourage development
Correct answer: A finding that they are necessary due to local climatic, geological, or topographical conditions
State laws that authorize local governments to amend model building codes typically require the local jurisdiction to make an express finding that the changes are reasonably necessary because of local climatic, geological, or topographical conditions. These amendments are generally required to be as or more restrictive than the base code.
Question 26: Which type of estimate is typically prepared from schematic or preliminary drawings and is least accurate?
- Bid estimate
- Conceptual (order of magnitude) estimate (Correct answer)
- Definitive estimate
- Detailed estimate
Correct answer: Conceptual (order of magnitude) estimate
A conceptual or order-of-magnitude estimate uses minimal design information and carries the widest range of accuracy, often ±30–50%.
Question 27: A supported scaffold on a construction site will be used by workers during the next shift. According to OSHA regulations, who must inspect the scaffold and when must this inspection occur?
- The site superintendent, only after it is first erected.
- A competent person, before each work shift. (Correct answer)
- A qualified engineer, at the beginning of the project.
- A project manager, at the end of each week.
Correct answer: A competent person, before each work shift.
OSHA standard 29 CFR 1926.451(f)(3) mandates that scaffolds and their components be inspected for visible defects by a competent person before each work shift and after any event that could affect the scaffold's structural integrity.
Question 28: In the context of construction scheduling, what does 'resource leveling' mean?
- Distributing materials evenly across the site
- Balancing the budget between phases
- Adjusting the schedule to smooth out peaks and valleys in resource demand (Correct answer)
- Equalizing profit across all subcontractors
Correct answer: Adjusting the schedule to smooth out peaks and valleys in resource demand
Resource leveling adjusts activity timing to avoid over- or under-utilization of labor, equipment, or materials at any point in time.
Question 29: According to ASTM standards, what minimum cure time is generally specified before testing concrete cylinder specimens for compressive strength?
- 3 days
- 14 days
- 7 days
- 28 days (Correct answer)
Correct answer: 28 days
ASTM C39 specifies 28-day cylinder tests as the standard acceptance criterion because portland cement concrete reaches approximately 99% of its design strength at that age.
Question 30: A general contractor is creating a construction schedule for a new single-family home. Which scheduling method identifies the sequence of tasks that determines the shortest possible project duration, where a delay in any task on this path will delay the entire project?
- Gantt Chart
- Line of Balance
- Program Evaluation and Review Technique (PERT)
- Critical Path Method (CPM) (Correct answer)
Correct answer: Critical Path Method (CPM)
The Critical Path Method (CPM) is a scheduling technique that identifies the longest sequence of dependent tasks (the 'critical path') through the project. This path determines the minimum time to complete the project. Any delay to a task on the critical path will directly extend the project's completion date.
Question 31: An owner terminates a contract 'for convenience' without cause. What is the contractor typically entitled to?
- Nothing, since the owner has the right to terminate
- The full contract price as if the project were completed
- Only payment for work completed to date
- Payment for work done, costs incurred, and lost profit on unperformed work (Correct answer)
Correct answer: Payment for work done, costs incurred, and lost profit on unperformed work
A for-convenience termination clause entitles the contractor to payment for completed work, committed costs, and anticipated profit on the remaining scope.
Question 32: Which of the following best describes 'value engineering' during the planning phase?
- Estimating project value for insurance purposes
- Increasing scope to add value for the owner
- Analyzing project components to achieve required function at lower cost without sacrificing quality (Correct answer)
- Adjusting bids to match the engineer's estimate
Correct answer: Analyzing project components to achieve required function at lower cost without sacrificing quality
Value engineering systematically reviews design and materials to find cost-effective alternatives that meet the same functional requirements.
Question 33: What is the PRIMARY purpose of a pre-construction meeting?
- Establishing project communication protocols, schedules, and expectations among all parties (Correct answer)
- Conducting a formal safety audit
- Finalizing the bid amount
- Obtaining building permits
Correct answer: Establishing project communication protocols, schedules, and expectations among all parties
The pre-construction meeting aligns the owner, architect, contractor, and subcontractors on communication channels, submittals, scheduling, and project procedures before work begins.
Question 34: An employer is required to maintain records of work-related injuries and illnesses. Which OSHA form serves as the detailed incident report for each individual recordable case?
- Form 300A (Summary of Work-Related Injuries and Illnesses)
- Form I-9 (Employment Eligibility Verification)
- Form 300 (Log of Work-Related Injuries and Illnesses)
- Form 301 (Injury and Illness Incident Report) (Correct answer)
Correct answer: Form 301 (Injury and Illness Incident Report)
OSHA's recordkeeping system uses three forms. Form 301 is the Injury and Illness Incident Report, which is used to capture detailed information about each specific incident. Form 300 is the log where all incidents are tracked throughout the year, and Form 300A is the annual summary that gets posted for employees to see.
Question 35: A worker suffers an amputation on a construction site. How quickly must the general contractor report this incident to OSHA?
- Within 8 hours
- Within 24 hours (Correct answer)
- Within 48 hours
- Within 72 hours
Correct answer: Within 24 hours
OSHA requires that any work-related amputation, inpatient hospitalization, or loss of an eye be reported within 24 hours.
Question 36: What is the significance of the 'Notice to Proceed' (NTP) in project planning?
- It is the contractor's formal acceptance of a subcontract
- It is required before a bond can be issued
- It is the owner's written authorization for the contractor to begin work, starting the contract clock (Correct answer)
- It signals completion of the punch list
Correct answer: It is the owner's written authorization for the contractor to begin work, starting the contract clock
The NTP is the formal owner directive that officially starts the project and triggers the contract's time for completion.
Question 37: A contractor working as a sole proprietor is personally sued for a project dispute. What is their exposure?
- Limited to the project contract amount
- Limited to the value of the business assets only
- Protected by contractor licensing laws
- Unlimited — all personal assets can be at risk (Correct answer)
Correct answer: Unlimited — all personal assets can be at risk
Sole proprietors have no legal separation between personal and business assets, so all personal property can be reached by business creditors.
Question 38: A project's direct costs are $800,000 and overhead is 12%. What is the total cost before profit?
- $812,000
- $888,000
- $896,000 (Correct answer)
- $860,000
Correct answer: $896,000
$800,000 × 1.12 = $896,000 total cost before profit.
Question 39: A client has requested a significant change to the HVAC system in a commercial building project that is already 50% complete. This change will affect the project's cost and schedule. What is the FIRST document the general contractor should prepare to address this request?
- A Request for Information (RFI)
- A Project Schedule Update
- A Change Order (Correct answer)
- A Subcontractor Agreement Amendment
Correct answer: A Change Order
A Change Order is a formal document that amends the original contract to reflect modifications in scope, cost, or schedule. When a client requests a significant change, a change order is necessary to document the new requirements, the associated cost increase or decrease, and any impact on the project timeline before the work proceeds.
Question 40: Under the Miller Act, a payment bond on federal construction projects protects which party?
- Subcontractors and suppliers who are not paid (Correct answer)
- The general contractor against owner nonpayment
- The federal government against contractor default
- Surety companies from excessive claims
Correct answer: Subcontractors and suppliers who are not paid
The Miller Act requires payment bonds on federal projects over $150,000 to protect subcontractors and material suppliers who cannot file mechanics liens on federal property.
Question 41: If a project's Cost Performance Index (CPI) is 0.85, this means the project is:
- 15% ahead of schedule
- Getting $0.85 of work done for every $1.00 spent — over budget (Correct answer)
- Ahead of budget by 15%
- Earning 85% more than planned
Correct answer: Getting $0.85 of work done for every $1.00 spent — over budget
A CPI below 1.0 indicates cost overrun; the project is spending more than the value of work accomplished.
Question 42: A general contractor submits a bid that contains a clerical error making it significantly lower than intended. Before the contract is signed, can the contractor withdraw the bid?
- Only if the bid bond is forfeited first
- No, all submitted bids are irrevocable
- Yes, if the error is proven and withdrawal is prompt (Correct answer)
- Only if the owner agrees to re-bid the project
Correct answer: Yes, if the error is proven and withdrawal is prompt
Most states allow bid withdrawal based on a material clerical error if the contractor promptly notifies the owner before contract execution and can prove the mistake.
Question 43: A subcontractor walks off the job due to a payment dispute with the general contractor. Under the terms of a standard subcontract, what is the general contractor's MOST appropriate immediate action?
- Withhold payment from all other subcontractors as leverage
- Terminate the subcontract immediately without notice
- Declare the subcontractor in default and issue a cure notice (Correct answer)
- File a mechanic's lien against the subcontractor
Correct answer: Declare the subcontractor in default and issue a cure notice
Most subcontracts require a written cure notice giving the subcontractor an opportunity to remedy the default before termination can proceed.
Question 44: What is the purpose of control joints in a concrete slab?
- To allow reinforcement placement
- To separate the slab from the footing
- To provide drainage pathways
- To create planes of weakness that control cracking location (Correct answer)
Correct answer: To create planes of weakness that control cracking location
Control joints are tooled or sawn grooves that create intentional weak planes so that shrinkage cracks occur at planned locations.
Question 45: Concrete consolidation by mechanical vibration is done primarily to:
- Increase the water-cement ratio for workability
- Eliminate air voids and ensure complete aggregate encapsulation (Correct answer)
- Create a smooth troweled surface finish
- Speed up the hydration process
Correct answer: Eliminate air voids and ensure complete aggregate encapsulation
Internal vibration removes entrapped air pockets and ensures concrete flows around reinforcement and into form corners for a dense, uniform matrix.
Question 46: Under a cost-plus contract with a Guaranteed Maximum Price (GMP), what happens if final project costs fall below the GMP?
- Savings may be shared between the owner and contractor per the contract terms (Correct answer)
- The owner keeps all savings automatically
- The contract is void and must be renegotiated
- The contractor must refund the unused contingency to the government
Correct answer: Savings may be shared between the owner and contractor per the contract terms
GMP contracts typically include a savings clause that specifies how cost savings below the maximum price are split between owner and contractor.
Question 47: Covered under a contractor's commercial general liability policy are:
- Warranty work
- Damage or injury as a result of the contractor's work (Correct answer)
- Contractors workmanship and Warranty work
- The contractor's workmanship
Correct answer: Damage or injury as a result of the contractor's work
A contractor's commercial general liability (CGL) policy primarily covers third-party bodily injury or property damage that occurs as a result of the contractor's operations. It is designed to protect against claims from accidents or negligence causing harm to others or their property. It does not typically cover the contractor's own faulty workmanship or warranty work, which are usually addressed by specific performance bonds or contractual obligations.
Question 48: Which OSHA standard covers hazard communication (HazCom) and requires Safety Data Sheets (SDS) on construction sites?
- 29 CFR 1910.1200 (Correct answer)
- 29 CFR 1910.132
- 29 CFR 1926.50
- 29 CFR 1926.100
Correct answer: 29 CFR 1910.1200
The Hazard Communication Standard is 29 CFR 1910.1200, which applies to construction sites via 1926.59.
Question 49: Under OSHA, which type of respirator provides the highest level of respiratory protection?
- Half-face air-purifying respirator
- Self-contained breathing apparatus (SCBA) (Correct answer)
- Powered air-purifying respirator (PAPR)
- Full-face air-purifying respirator
Correct answer: Self-contained breathing apparatus (SCBA)
SCBA provides the highest protection level because it supplies breathable air from a portable tank, independent of the surrounding atmosphere.
Question 50: A general contractor is beginning site work for a new commercial building in a developed area. What is the legally mandated first step that must be taken to identify and prevent damage to existing underground public utilities?
- Contact the national "Call Before You Dig" service by dialing 811. (Correct answer)
- Carefully excavate with a backhoe until a utility is found.
- Hire a private utility locator to scan the entire property with ground-penetrating radar.
- Review the original as-built drawings from when the area was first developed.
Correct answer: Contact the national "Call Before You Dig" service by dialing 811.
State and federal law requires anyone who plans to excavate to contact their state's one-call utility location service, which is universally accessible by dialing 811. This service notifies member utility companies, who then send locators to mark the approximate location of their underground lines, preventing costly and dangerous utility strikes.
Question 51: Which fire-resistance rating is typically required for a floor-ceiling assembly separating dwelling units in a two-family residential building?
- 2 hours
- 30 minutes
- 45 minutes
- 1 hour (Correct answer)
Correct answer: 1 hour
IBC and IRC typically require a minimum 1-hour fire-resistance rating for floor-ceiling assemblies separating dwelling units to allow safe egress time in the event of fire.
Question 52: Which document defines the full scope of work that a contractor must perform on a project?
- Notice to proceed
- Bid bond
- Scope of work / specifications (Correct answer)
- Change order log
Correct answer: Scope of work / specifications
The scope of work, typically detailed in the specifications and contract documents, defines exactly what the contractor is required to perform.
General Contractor License Exam (Business & Law Portion)
This exam certifies individuals in the business and legal aspects of operating a general contracting business, covering regulations, contracts, and financial management.
Exam Rules
- You can skip questions and return to them later
- Flag questions for review before submitting
- No feedback shown until you submit the entire exam
- Unanswered questions count as wrong — answer everything
- 10 pretest questions are mixed in and don't affect your score
- Timer auto-submits when time runs out
- Your progress is auto-saved every 30 seconds