What is 'substantial completion' in a construction contract?
-
A
When 50% of the contract value is earned
-
B
The stage when the work is sufficiently complete for the owner to use it for its intended purpose
-
C
Final payment to all subcontractors
-
D
Issuance of a temporary certificate of occupancy