General Contractor License Project Management and Supervision Questions and Answers

A client has requested a significant change to the HVAC system in a commercial building project that is already 50% complete.
This change will affect the project's cost and schedule.

What is the FIRST document the general contractor should prepare to address this request?

Select your answer