A subcontractor falls behind schedule on a critical-path activity. What is the MOST appropriate first step for the general contractor?
-
A
Terminate the subcontractor immediately
-
B
Issue a formal cure notice and schedule a recovery meeting
-
C
Absorb the delay and extend the project end date
-
D
Bill the owner for additional supervision costs