A project owner verbally directs the contractor to add extra work not covered by the contract but refuses to issue a written change order. What should the contractor do?
-
A
Proceed with the work since the owner gave verbal authorization
-
B
Decline to start the extra work until a written change order or written direction is provided
-
C
Complete the work and absorb the cost to maintain the owner relationship
-
D
Submit a mechanic's lien immediately for the anticipated extra cost