A general contractor is preparing a bid for a lump-sum contract. Which cost element is most commonly overlooked that can lead to project losses?
-
A
Labor wages listed in the plans
-
B
General conditions and overhead costs
-
C
Material quantities from the drawings
-
D
Subcontractor scope items