A subcontractor's bid is missing clarifications on exclusions. What should the GC do before including it in the bid?
-
A
Use the bid as submitted to stay competitive
-
B
Contact the subcontractor to clarify scope before bid day
-
C
Add a 20% contingency and include it
-
D
Exclude the sub and use the next lowest