A contractor is performing work on a project and discovers the job will exceed their license monetary limit. They should:
-
A
Continue working since the limit is rarely enforced
-
B
Stop work and refer the project to a contractor with an appropriate license limit
-
C
Apply for a higher limit retroactively after project completion
-
D
Subcontract the excess value to themselves under a different business name