A general contractor is hired under a cost-plus contract with a guaranteed maximum price (GMP). If actual costs exceed the GMP, who bears the additional cost?
-
A
The owner, since it is cost-plus
-
B
The contractor, since the GMP is the ceiling
-
C
Both parties share equally above the GMP
-
D
The subcontractors through back-charges