A healthcare project manager notices that a key vendor is consistently delivering materials late. Which proactive step should be taken FIRST?
-
A
Terminate the vendor contract immediately
-
B
Issue a formal cure notice and meet with the vendor to understand root causes
-
C
Accept the delays and extend the project schedule
-
D
Hire a second vendor without notifying the first