Free CHFM Certification Question and Answers — Questions and Answers
Question 1: Which of the following is LEAST likely to be on a punch list for a project that is essentially finished?
- Plugged condensate drain in HVAC unit
- Missing hand railing in geriatrics ward
- Equipment planning for an expansion project (Correct answer)
- Cracked fascia over waiting room entrance
Correct answer: Equipment planning for an expansion project
A punch list is a document generated near the end of a construction or renovation project, detailing items that are incomplete, incorrect, or not in compliance with project specifications. It focuses on rectifying deficiencies within the *current* project before final closeout. Equipment planning for an *expansion project* is a future-oriented task related to a new or separate endeavor, not a corrective action for an essentially finished project, making it the least likely item on a punch list.
Question 2: Which of the following best describes socially responsible design?
- The design complies with HIPAA (health Insurance Portability and Accountability Act) privacy law
- The design should not significantly increase capital cost on paper-bed basis
- The design should allow for acuity-adaptable patient rooms for the critically ill
- The design is based on information gathered from visits to other facilities (Correct answer)
Correct answer: The design is based on information gathered from visits to other facilities
Socially responsible design in healthcare emphasizes creating environments that positively impact patients, staff, and the community. Gathering information from visits to other facilities allows designers to observe successful design solutions in real-world settings, understand their impact on user experience and operational efficiency, and adapt best practices. This approach ensures the design is informed by practical application and user needs, leading to more effective and beneficial healthcare spaces.
Question 3: Which of the following can be determined via a condition assessment?
- A price ceiling for alterations
- How to plan and schedule maintenance
- The feasibility of a facility relocation
- How to properly allocate and spend funds (Correct answer)
Correct answer: How to properly allocate and spend funds
A condition assessment systematically evaluates the physical state, functional performance, and remaining useful life of a facility's assets and systems. By identifying current deficiencies, potential risks, and future capital needs, it provides crucial data for strategic planning and budgeting. This assessment helps facility managers understand where investments are most needed, prioritize repairs and upgrades, and justify financial requests, ensuring funds are allocated and spent effectively to maintain and improve the facility.
Question 4: What is the purpose of the Maintenance Manual's Policy & Procedures (P & P) section?
- To aid HR departments when they are disciplining staff and preparing out cases (Correct answer)
- To enable the CHFM to coordinate with emergency services
- To assist security in controlling access to equipment utility rooms
- To prioritize measures that need to be taken during the power outage
Correct answer: To aid HR departments when they are disciplining staff and preparing out cases
The Policy & Procedures (P&P) section of a Maintenance Manual outlines the standardized methods, rules, and expectations for performing maintenance tasks, ensuring consistency, safety, and compliance. These documented procedures are essential for HR departments when addressing performance issues or disciplinary actions, as they provide clear, objective benchmarks for expected staff conduct and task execution. They serve as evidence of established protocols that employees are expected to follow.
Question 5: Which of the following is determined after reviewing the facility blueprints?
- Space for additional insulation (Correct answer)
- The effectiveness of maintenance
- Access control to utility rooms
- The location of blocked roof drains
Correct answer: Space for additional insulation
Facility blueprints provide detailed architectural and engineering drawings of a building, including structural elements, wall cavities, and existing insulation specifications. By reviewing these blueprints, a CHFM can identify available spaces within walls, ceilings, or attics where additional insulation could be installed to improve energy efficiency. The blueprints reveal the physical constraints and opportunities for such modifications, which is crucial for planning such upgrades.
Question 6: When is it most common to employ an indefinite quantity contract?
- When in-house staff and contractors are being used and flexibility is needed
- When the contractor uses a job book while bidding on work
- When a facility outsources its management
- When repair work on flooring, walls, and ceilings of a facility is being done (Correct answer)
Correct answer: When repair work on flooring, walls, and ceilings of a facility is being done
An indefinite quantity contract (also known as an on-call or term contract) is most commonly used for recurring maintenance or repair work where the exact quantity or timing of services is not known in advance. For routine repairs like flooring, walls, and ceilings, a facility can establish a contract with a vendor to perform these tasks as needed over a period, without having to bid each small job individually. This provides flexibility and efficiency for ongoing, unpredictable maintenance needs.
Question 7: What is included in a CMMS (Computer Maintenance Management System)?
- Estimates of capital equipment expenses
- Part list and diagrams from manual (Correct answer)
- Engineering assessment related to code compliance
- Information about service contractor
Correct answer: Part list and diagrams from manual
A Computerized Maintenance Management System (CMMS) is designed to efficiently manage maintenance operations and asset information. A key component of a CMMS is its ability to store and organize detailed information about assets, including equipment manuals, part lists, and diagrams. This allows maintenance staff to quickly access necessary information for repairs, ordering parts, and understanding equipment configurations, thereby streamlining the maintenance process and improving efficiency.
Which of the following is LEAST likely to be on a punch list for a project that is essentially finished?