Which risk response strategy is most appropriate when a healthcare construction project faces a regulatory uncertainty that cannot be eliminated?
-
A
Avoid the risk by canceling the project
-
B
Mitigate the risk by reducing its probability
-
C
Accept the risk and establish a contingency reserve
-
D
Transfer the risk to the contractor