A healthcare facility manager is preparing a capital budget request for a new HVAC system. Which financial metric best demonstrates the project's long-term value to administration?
-
A
Payback period only
-
B
Net present value (NPV)
-
C
Gross revenue impact
-
D
Total depreciation amount