What is the primary role of a project charter in a healthcare facility capital project?
-
A
To outline the detailed construction schedule and milestones
-
B
To formally authorize the project and define its scope, objectives, and key stakeholders
-
C
To document all change orders approved during construction
-
D
To specify the procurement method for selecting contractors