What is the primary purpose of a construction phasing plan in a healthcare facility renovation project?
-
A
To allow construction to proceed while minimizing disruption to patient care and maintaining compliance
-
B
To document the order in which subcontractors will be paid
-
C
To satisfy TJC requirements for construction documentation
-
D
To establish the renovation budget by phase