A grant recipient discovers mid-project that a key subcontractor cannot complete their scope of work. What is the FIRST step the grant administrator should take?
-
A
Immediately terminate the subcontract and find a replacement
-
B
Review the grant agreement for prior approval requirements before making changes
-
C
Notify the grantor only after a replacement subcontractor is secured
-
D
Continue the project and document the issue in the final report