According to NFPA 72, what is the required initial and subsequent testing frequency for smoke detector sensitivity?
Select your answer
A
Initially within 6 months of installation, and annually thereafter.
B
Initially within 1 year of installation, then every alternate year. If two consecutive tests are stable, the interval can extend to 5 years.
C
Annually from the date of installation for the life of the detector.
D
Only when a trouble signal indicates a sensitivity issue on the FACP.