A new Scrum Master believes Scrum is a process that, once correctly implemented, never needs to change. What is wrong with this view?
-
A
Scrum does allow process changes, but only after six months
-
B
Scrum's empirical nature requires ongoing inspection and adaptation of how the team works
-
C
The Scrum Guide prohibits changes to the team's working agreement
-
D
Only the Product Owner can authorize changes to team processes