Professional Scrum Master Scrum Theory and Principles 4 — Questions and Answers
Question 1: A new Scrum Master believes Scrum is a process that, once correctly implemented, never needs to change. What is wrong with this view?
- Scrum does allow process changes, but only after six months
- Scrum's empirical nature requires ongoing inspection and adaptation of how the team works (Correct answer)
- The Scrum Guide prohibits changes to the team's working agreement
- Only the Product Owner can authorize changes to team processes
Correct answer: Scrum's empirical nature requires ongoing inspection and adaptation of how the team works
Empiricism in Scrum demands continuous inspection and adaptation — the team's processes must evolve as they learn from experience.
Question 2: Which statement about the relationship between Scrum values and the three pillars of empiricism is most accurate?
- The values and pillars are independent; neither influences the other
- The Scrum values enable the pillars — without lived values, transparency, inspection, and adaptation fail (Correct answer)
- The three pillars replace the need for Scrum values in mature teams
- The pillars are theoretical while the values are the only practical component
Correct answer: The Scrum values enable the pillars — without lived values, transparency, inspection, and adaptation fail
The Scrum values (courage, focus, commitment, respect, openness) create the conditions under which the three empirical pillars can function effectively.
Question 3: During Sprint Planning, the team selects more work than they can likely complete. Which Scrum value is being violated?
- Courage
- Respect
- Commitment (Correct answer)
- Openness
Correct answer: Commitment
Commitment means making realistic, meaningful promises — selecting more work than the team can complete is an uncommitted or dishonest forecast.
Question 4: What distinguishes a 'complex' problem domain from a 'complicated' one, and why does this matter for Scrum?
- Complex problems have known solutions; complicated ones do not
- Complex problems have unknown solutions requiring experimentation; Scrum is optimized for this environment (Correct answer)
- Complex problems are solved by adding more people; Scrum limits team size instead
- Complex and complicated are synonyms in the Scrum context
Correct answer: Complex problems have unknown solutions requiring experimentation; Scrum is optimized for this environment
Complex problems (like innovative product development) have emergent solutions that can't be fully predicted — Scrum's empirical cycles are designed precisely for this environment.
Question 5: A Scrum Team shares their Sprint Backlog only within the team and does not make it visible to stakeholders. Which pillar is compromised?
- Adaptation
- Inspection
- Transparency (Correct answer)
- Commitment
Correct answer: Transparency
Transparency requires that significant aspects of the process be visible to those responsible for the outcome — hiding the Sprint Backlog limits shared understanding.
Question 6: The Scrum Guide says Scrum is 'simple to understand, difficult to master.' What makes mastery difficult?
- The rules and roles are complex and frequently change
- Changing organizational culture and team behaviors to truly live Scrum values is hard (Correct answer)
- The technical practices required by Scrum are too advanced for most teams
- Scrum requires specialized certifications before teams can practice it
Correct answer: Changing organizational culture and team behaviors to truly live Scrum values is hard
The rules of Scrum are simple, but genuinely living the values and maintaining the discipline of empiricism requires significant cultural and behavioral change.
Question 7: A Scrum Team is under pressure to skip the Sprint Review to save time. What is the greatest risk of doing so?
- The team loses the opportunity to update their velocity metrics
- Stakeholders lose the ability to inspect the Increment and adapt the Product Backlog (Correct answer)
- The Scrum Master cannot update the burndown chart
- Developers cannot receive their performance reviews
Correct answer: Stakeholders lose the ability to inspect the Increment and adapt the Product Backlog
The Sprint Review is the formal inspection of the Increment by stakeholders, enabling adaptation of the Product Backlog — skipping it cuts off a critical empirical feedback loop.
A new Scrum Master believes Scrum is a process that, once correctly implemented, never needs to change.
What is wrong with this view?