A Scrum Team is mid-Sprint when a stakeholder requests an urgent change. What should the Scrum Master do?
-
A
Halt the Sprint immediately and re-plan
-
B
Add the item to the current Sprint Backlog
-
C
Direct the stakeholder to bring it up at the next Sprint Review
-
D
Encourage the Product Owner to negotiate scope with the Development Team