Professional Scrum Master Scrum Events and Activities 2 — Questions and Answers
Question 1: A Scrum Team is mid-Sprint when a stakeholder requests an urgent change. What should the Scrum Master do?
- Halt the Sprint immediately and re-plan
- Add the item to the current Sprint Backlog
- Direct the stakeholder to bring it up at the next Sprint Review
- Encourage the Product Owner to negotiate scope with the Development Team (Correct answer)
Correct answer: Encourage the Product Owner to negotiate scope with the Development Team
The Product Owner can negotiate scope with the Development Team during a Sprint without cancelling it; only the Product Owner can cancel a Sprint.
Question 2: How long is the recommended timebox for a Sprint Planning event in a two-week Sprint?
- 2 hours
- 4 hours (Correct answer)
- 8 hours
- 1 hour
Correct answer: 4 hours
Sprint Planning is timeboxed to a maximum of 8 hours for a one-month Sprint, so roughly 4 hours for a two-week Sprint.
Question 3: Which statement about the Daily Scrum is correct?
- The Scrum Master must facilitate it every day
- Only Developers are required to attend (Correct answer)
- Stakeholders may attend to provide updates
- The Product Owner sets the agenda
Correct answer: Only Developers are required to attend
The Daily Scrum is an event for Developers; the Scrum Master and Product Owner attend only if they are also doing development work.
Question 4: What is the primary outcome expected from the Sprint Retrospective?
- A prioritized Product Backlog
- An updated Definition of Done
- At least one actionable improvement for the next Sprint (Correct answer)
- A stakeholder satisfaction report
Correct answer: At least one actionable improvement for the next Sprint
The Scrum Team identifies improvements and commits to implementing at least one in the next Sprint.
Question 5: During Sprint Planning, the Development Team realizes the Sprint Goal cannot be achieved within the Sprint timebox. What should happen?
- The Scrum Master extends the Sprint
- The team negotiates scope with the Product Owner to fit the timebox (Correct answer)
- The Sprint is cancelled before it starts
- The Product Owner removes the Sprint Goal
Correct answer: The team negotiates scope with the Product Owner to fit the timebox
Teams negotiate which Product Backlog Items support the Sprint Goal so the work fits within the timebox.
Question 6: Who is responsible for ensuring the Sprint Review takes place?
- The Development Team
- The Product Owner
- The Scrum Master (Correct answer)
- The Stakeholders
Correct answer: The Scrum Master
The Scrum Master is accountable for ensuring all Scrum events occur and are positive, productive, and kept within the timebox.
Question 7: A team skips the Sprint Retrospective because they feel the Sprint went perfectly. What is the risk?
- The next Sprint Planning will be invalid
- The Definition of Done cannot be updated
- Continuous improvement opportunities are missed and the team may not inspect its processes (Correct answer)
- The Product Owner must cancel the next Sprint
Correct answer: Continuous improvement opportunities are missed and the team may not inspect its processes
Even in successful Sprints, retrospectives provide the opportunity to inspect and adapt, preventing process stagnation.
A Scrum Team is mid-Sprint when a stakeholder requests an urgent change.
What should the Scrum Master do?