In a Monte Carlo simulation of project cost, what does the P80 value on the cumulative S-curve represent?
-
A
An 80% chance the actual cost will be at or below that value
-
B
An 80% chance the cost will exceed that value
-
C
The cost is 80% of the deterministic estimate
-
D
The 80th iteration of the simulation