During the Plan Risk Management process, the project manager and team establish the methodology, roles, and responsibilities for risk management. Which of the following is a key output of this process that documents these decisions and serves as a guide for all subsequent risk management activities?
-
A
Risk Register
-
B
Risk Management Plan
-
C
Stakeholder Engagement Plan
-
D
Risk Breakdown Structure (RBS)