A project manager discovers that a key stakeholder has shifted from supportive to resistant after a scope change. What should the project manager do FIRST?
-
A
Escalate to the project sponsor
-
B
Conduct a stakeholder analysis to understand the change in position
-
C
Remove the stakeholder from the communication plan
-
D
Proceed without addressing the concern