What is the Cost Performance Index (CPI) formula and what does a CPI of 0.85 indicate?
-
A
CPI = PV/AC; the project is over budget
-
B
CPI = EV/AC; for every dollar spent, only $0.85 of value is being produced (over budget)
-
C
CPI = AC/EV; the project is under budget
-
D
CPI = EV/PV; the project is behind schedule