A project manager is leading a large construction project in a country with strict, newly-enacted environmental laws. The project sponsor is focused on accelerating the schedule. During a project review, the project manager notes that incorporating the new compliance activities will cause a significant schedule delay. What is the project manager's MOST appropriate first action?
-
A
Request additional budget from the sponsor to cover the costs of non-compliance fines.
-
B
Proceed with the original plan to meet the sponsor's schedule expectations and address compliance issues later.
-
C
Analyze the consequences of non-compliance and present a revised plan to the governance board that incorporates the mandatory legal requirements.
-
D
Delegate all compliance-related tasks to the legal department without adjusting the project plan.