A project delivered a new automated invoicing system, which was completed on time and within budget. However, six months after implementation, the accounting department reports that the expected 20% reduction in processing time has not been achieved. Which project document should be consulted to understand the plan for tracking and measuring this specific post-project value?
-
A
Project Charter
-
B
Business Case
-
C
Benefits Management Plan
-
D
Scope Statement