A project manager is leading a software development project. To address the risk of a critical server failing, the team implements a redundant server that will take over automatically. However, this response introduces a new risk: the failover process itself could corrupt data. According to the PMBOK® Guide, what is this new risk called?
-
A
Residual risk
-
B
Secondary risk
-
C
Contingency risk
-
D
Accepted risk